AFCONS 2

AFCONS (NAGPUR METRO RAIL PROJECT)

  • Completed Reach 3 project construction of precast post tension I -Girder and site construction work of portal
  • Completed Reach 1 precast RCC I- Girder
  • Completed Reach 2 precast post tension I- Girder

QUALITY BUILDCON

QUALITY BUILDCON (Mega Metro project Ahmadabad)

  • Precast pre tensioned I -Girder

CEC

CEC(NOIDA METRO RAIL PROJECT)

  • Supply of Laborers for cleaning and finishing of viaduct

ITD

ITD (NAGPUR)

  • Construction of post tension I-Girder

AFCONS

AFCONS (NAGPUR METRO RAIL PROJECT)

  • Working for precast wings

NCC

NCC (DELHI)

  • Measurement work at site (Airport terminal1D)

APCO

NCRTC PROJECT (DELHI TO MEERUT)

This Project was started on July 2021

  • Worked on Post-Tensioned I Girder

AFCONS

NCRTC PROJECT (DELHI TO MEERUT)

This Project was started on July 2021

  • Working on Post-Tensioned I Girder